Alinda Villas Construction Update Plot 2
We are thrilled to showcase the remarkable construction progress of our Alinda Villas project!
-
OVERVIEW
-
FOUNDATION FOOTING PROCESS 100 %
-
STRUCTURE PROCESS 100 %
-
ARCHITECTURAL PROCESS 99 %
– BRICK WORK 100 %
– PIPE LINE INSTALLATION 100 %
– PLASTERING WORK 100 %
-
ARCHITECTURAL PROCESS 99 %
– FINISHING & MATERIAL INSTALLATION WORK 95%
-
ARCHITECTURAL PROCESS 99 %
– PAINTING WORK 100 %
-
DECORATIVE WORK AND TRANSFER PROCESS 92.5 %
– GARDENING WORK 100 %
-
DECORATIVE WORK AND TRANSFER PROCESS 92.5 %
-BUILT IN WORK 85 %
STATUS SUMMARY
-
FOUNDATION FOOTING PROCESS 100 %
-
STRUCTURE PROCESS 100 %
-
ARCHITECTURAL PROCESS 99 %
– BRICK WORK 100 %
– PIPE LINE INSTALLATION 100 %
– PLASTERING WORK 100 %
– FINISHING & MATERIAL INSTALLATION WORK 95 %
– PAINTING WORK 100 % -
DECORATIVE WORK AND TRANSFER PROCESS 92.5 %
-GARDENING WORK 100 %
-BUILT IN WORK 85 %