Alinda Villas Construction Update Plot 3

FOUNDATION FOOTING PROCESS 100%

STRUCTURE PROCESS 95%
– GROUND BEAM AND FLOOR STRUCTURE PROCESS      95%
– POOL AND SURGE TANK STRUCTURE PROCESS            95%
– COLUMN                                                                                 95%
– ROOF BEAM AND ROOF SLAB                                             95%

ARCHITECTURAL PROCESS 65 %
– BRICK WORK 92 %

ARCHITECTURAL PROCESS 65 %
– PIPE LINE INSTALLATION 75 %

ARCHITECTURAL PROCESS 65 %
– PLASTERING WORK 75 %

ARCHITECTURAL PROCESS 65 %
– FINISHING & MATERIAL INSTALLATION WORK 40 %

ARCHITECTURAL PROCESS 65 %
– PAINTING WORK 45 %

STATUS SUMMARY
FOUNDATION FOOTING PROCESS 100 %
STRUCTURE PROCESS 95 %
– GROUND BEAM AND FLOOR STRUCTURE PROCESS   95%
– POOL AND SURGE TANK STRUCTURE PROCESS         95%
– COLUMN                                                                              95%
– ROOF BEAM AND ROOF SLAB                                          95%
ARCHITECTURAL PROCESS 65 %
– BRICK WORK       92%
– PIPE LINE INSTALLATION        75%
– PLASTERING WORK                 75%
– FINISHING & MATERIAL INSTALLATION WORK     40%
– PAINTING WORK                       45%
DECORATIVE WORK AND TRANSFER PROCESS 0 %