Alinda Villas Construction Update Plot 5
We are thrilled to showcase the remarkable construction progress of our Alinda Villas project!
-
OVERVIEW

-
FOUNDATION FOOTING PROCESS 100 %
-
STRUCTURE PROCESS 100 %
-
ARCHITECTURAL PROCESS 52 %
– BRICK WORK 90 %
-
ARCHITECTURAL PROCESS 52 %
– PIPE LINE INSTALLATION

-
ARCHITECTURAL PROCESS 52 %
– PLASTERING WORK 60%

-
ARCHITECTURAL PROCESS 52 %
– FINISHING & MATERIAL INSTALLATION WORK 15 %

-
ARCHITECTURAL PROCESS 52 %
– PAINTING WORK 30 %

-
DECORATIVE WORK AND TRANSFER PROCESS 0 %
STATUS SUMMARY
-
FOUNDATION FOOTING PROCESS 100 %
-
STRUCTURE PROCESS 100%
-
ARCHITECTURAL PROCESS 52 %
– BRICK WORK 90 %
– PIPE LINE INSTALLATION 65 %
– PLASTERING WORK 60 %
– FINISHING & MATERIAL INSTALLATION WORK 15 %
– PAINTING WORK 30 % -
DECORATIVE WORK AND TRANSFER PROCESS 0 %