Alinda Villas Construction Update Plot 5

We are thrilled to showcase the remarkable construction progress of our Alinda Villas project!
  • OVERVIEW

  • FOUNDATION FOOTING PROCESS 100 %

  • STRUCTURE PROCESS 100 %

  • ARCHITECTURAL PROCESS 52 %

    – BRICK WORK 90 %

  • ARCHITECTURAL PROCESS 52 %

    – PIPE LINE INSTALLATION

  • ARCHITECTURAL PROCESS 52 %

    – PLASTERING WORK 60%

  • ARCHITECTURAL PROCESS 52 %

    – FINISHING & MATERIAL INSTALLATION WORK 15 %

  • ARCHITECTURAL PROCESS 52 %

    – PAINTING WORK 30 %

  • DECORATIVE WORK AND TRANSFER PROCESS 0 %

 

STATUS SUMMARY

  • FOUNDATION FOOTING PROCESS 100 %

  • STRUCTURE PROCESS 100%

  • ARCHITECTURAL PROCESS 52 %

    – BRICK WORK 90 %
    – PIPE LINE INSTALLATION 65 %
    – PLASTERING WORK 60 %
    – FINISHING & MATERIAL INSTALLATION WORK 15 %
    – PAINTING WORK 30 %

  • DECORATIVE WORK AND TRANSFER PROCESS 0 %