Alinda Villas Construction Update Plot 3
We are thrilled to showcase the remarkable construction progress of our Alinda Villas project!

CONSTRUCTION STATUS OF PLOT 3
- FOUNDATION FOOTING PROCESS 100 %
- STRUCTURE PROCESS 100 %
-
ARCHITECTURAL PROCESS 88 %
– BRICK WORK 100 %
– PIPE LINE INSTALLATION 100 %
– PLASTERING WORK 100 %
-
ARCHITECTURAL PROCESS 88 %
– FINISHING & MATERIAL INSTALLATION WORK 75%
-
ARCHITECTURAL PROCESS 88 %
– PAINTING WORK 75%

-
DECORATIVE WORK AND TRANSFER PROCESS 45 %
– GARDENTING WORK 90 %
-
DECORATIVE WORK AND TRANSFER PROCESS 45 %
– BUILT IN WORK 0 %
STATUS SUMMARY
-
FOUNDATION FOOTING PROCESS 100 %
-
STRUCTURE PROCESS 100 %
-
ARCHITECTURAL PROCESS 88 %
– BRICK WORK 100 %
– PIPE LINE INSTALLATION 100 %
– PLASTERING WORK 100 %
– FINISHING & MATERIAL INSTALLATION WORK 70 %
– PAINTING WORK 70 % -
DECORATIVE WORK AND TRANSFER PROCESS 45 %
– GARDENTING WORK 90 %
– BUILT IN WORK 0 %