Alinda Villas Construction Update Plot 3

We are thrilled to showcase the remarkable construction progress of our Alinda Villas project!

CONSTRUCTION STATUS OF PLOT 3

  • FOUNDATION FOOTING PROCESS 100 %
  • STRUCTURE PROCESS 100 %

  • ARCHITECTURAL PROCESS 88 %

    – BRICK WORK 100 %
    – PIPE LINE INSTALLATION 100 %
    – PLASTERING WORK 100 %

  • ARCHITECTURAL PROCESS 88 %

    – FINISHING & MATERIAL INSTALLATION WORK 75%

  • ARCHITECTURAL PROCESS 88 %

    – PAINTING WORK 75%

  • DECORATIVE WORK AND TRANSFER PROCESS 45 %

    – GARDENTING WORK 90 %

  • DECORATIVE WORK AND TRANSFER PROCESS 45 %

    – BUILT IN WORK 0 %

STATUS SUMMARY

  • FOUNDATION FOOTING PROCESS 100 %

  • STRUCTURE PROCESS 100 %

  • ARCHITECTURAL PROCESS 88 %

    – BRICK WORK 100 %
    – PIPE LINE INSTALLATION 100 %
    – PLASTERING WORK 100 %
    – FINISHING & MATERIAL INSTALLATION WORK 70 %
    – PAINTING WORK 70 %

  • DECORATIVE WORK AND TRANSFER PROCESS 45 %

    – GARDENTING WORK 90 %
    – BUILT IN WORK 0 %