Alinda Villas Construction Update Plot 2
We are thrilled to showcase the remarkable construction progress of our Alinda Villas project!
CONSTRUCTION STATUS OF PLOT 2
-FOUNDATION FOOTING PROCESS 100 %
-STRUCTURE PROCESS 100 %
-
ARCHITECTURAL PROCESS 96 %
– BRICK WORK 100 %
– PIPE LINE INSTALLATION 100 %
– PLASTERING WORK 100 %
-
ARCHITECTURAL PROCESS 96 %
– FINISHING & MATERIAL INSTALLATION WORK 90%
-
ARCHITECTURAL PROCESS 96 %
– PAINTING WORK 90 %
-
DECORATIVE WORK AND TRANSFER PROCESS 55 %
– GARDENTING WORK 90 %
-
DECORATIVE WORK AND TRANSFER PROCESS 55 %
– BUILT IN WORK 20 %
STATUS SUMMARY
-
FOUNDATION FOOTING PROCESS 100 %
-
STRUCTURE PROCESS 100 %
-
ARCHITECTURAL PROCESS 96 %
– BRICK WORK 100 %
– PIPE LINE INSTALLATION 100 %
– PLASTERING WORK 100 %
– FINISHING & MATERIAL INSTALLATION WORK 90 %
– PAINTING WORK 90 % -
DECORATIVE WORK AND TRANSFER PROCESS 55 %
– GARDENTING WORK 90 %
– BUILT IN WORK 20 %