Alinda Villas Construction Update Plot 2

We are thrilled to showcase the remarkable construction progress of our Alinda Villas project!

CONSTRUCTION STATUS OF PLOT 2

-FOUNDATION FOOTING PROCESS 100 %
-STRUCTURE PROCESS 100 %

 

  • ARCHITECTURAL PROCESS 96 %

– BRICK WORK 100 %
– PIPE LINE INSTALLATION 100 %
– PLASTERING WORK 100 %

  • ARCHITECTURAL PROCESS 96 %

    – FINISHING & MATERIAL INSTALLATION WORK 90%

  • ARCHITECTURAL PROCESS 96 %

    – PAINTING WORK 90 %

  • DECORATIVE WORK AND TRANSFER PROCESS 55 %

    – GARDENTING WORK 90 %

  • DECORATIVE WORK AND TRANSFER PROCESS 55 %

    – BUILT IN WORK 20 %

STATUS SUMMARY

  • FOUNDATION FOOTING PROCESS 100 %

  • STRUCTURE PROCESS 100 %

  • ARCHITECTURAL PROCESS 96 %

    – BRICK WORK 100 %
    – PIPE LINE INSTALLATION 100 %
    – PLASTERING WORK 100 %
    – FINISHING & MATERIAL INSTALLATION WORK 90 %
    – PAINTING WORK 90 %

  • DECORATIVE WORK AND TRANSFER PROCESS 55 %

    – GARDENTING WORK 90 %
    – BUILT IN WORK 20 %