Alinda Villas Construction Update Plot 9

We are thrilled to showcase the remarkable construction progress of our Alinda Villas project!
  • OVERVIEW

  • FOUNDATION FOOTING PROCESS 100 %

  • STRUCTURE PROCESS 46%

    – GROUND BEAM STRUCTURE PROCESS 85%

  • STRUCTURE PROCESS 46%

    – POOL AND SURGE TANK STRUCTURE PROCESS 80%

  • STRUCTURE PROCESS 46%

    – COLUMN 20 %

  • STRUCTURE PROCESS 46%

    -ROOF BEAM AND SLAB 0%

  • ARCHITECTURAL PROCESS 0 %

    -BRICK WORK 0 %
    -PIPE LINE INSTALLATION 0 %
    -PAINTING WORK 0 %
    -FINISHING & MATERIAL INSTALLATION WORK 0 %
    -PAINTING WORK 0 %

  • DECORATIVE WORK AND TRANSFER PROCESS 0 %

  • FOUNDATION FOOTING PROCESS 100 %

  • STRUCTURE PROCESS 46 %

    – GROUND BEAM STRUCTURE PROCESS 85 %
    – POOL AND SURGE TANK STRUCTURE PROCESS 80 %
    – COLUMN 20 %
    – ROOF BEAM AND SLAB 0 %

  • ARCHITECTURAL PROCESS 0%

    – BRICK WORK 0 %
    – PIPE LINE INSTALLATION 0 %
    – PLASTERING WORK 0 %
    – FINISHING & MATERIAL INSTALLATION WORK 0 %
    – PAINTING WORK 0 %

  • DECORATIVE WORK AND TRANSFER PROCESS 0 %